A 60-day build: how it works step by step

Short answer: a Dreams House home is built in 60 days counted from the first day of construction. It is shorter because most of the work is done in a factory and on the land the panels are only assembled.
Stage 1: project
The house is designed with you, to measure, and each panel is defined. It is the stage where the floor plan, the openings and the finishes are decided.
Stage 2: slab
The concrete slab is prepared on the land. Meanwhile, the factory begins to manufacture the panels.
Stage 3: manufacturing the panels
The panels are galvanized steel and are made in a factory, with controlled measurements. They arrive identified for each wall.
Stage 4: assembly
The panels are fixed to the slab and screwed to each other. Because the walls arrive made, the structure goes up in a few days.
Stage 5: enclosure and finishes
The wall is completed with insulation and boards inside and outside, the openings are installed and the finishes are done. The plumbing and electrical installations run inside the panels.
Why it is shorter
- There are no mixes that have to set.
- The walls arrive made and with exact measurements.
- There are fewer trades working at the same time and less rubble.
If you are thinking of building in steel framing, get to know Steel Panel first: the comparison is in SteelPanel vs steel framing.
What happens on the land, day by day
First the walls are laid out and marked, and the levels of the slab are checked. Then an asphalt membrane of at least 3 mm is placed under the line of the panels, to cut off the damp rising from the ground. The panels arrive numbered, are placed according to the project and are fixed to the slab with stainless steel anchor bolts. The panels are screwed to each other.
What is done at the factory in the meantime
While the base is prepared on the land, at the plant the zinc-coated steel modules of at least 0.8 mm are manufactured, the panels are assembled and each one is identified for its wall. The fact that so much of the work happens in parallel is what allows the build to be counted in days and not in months.
Frequently asked questions
From when are the 60 days counted?
From the first day of construction.
Is such a short build lower quality?
No. What is shortened is the work on the land. The house has a 40-year warranty.
How do I ask for a quote?
Message us on WhatsApp at +598 92 743 331 with the location of the land and an idea of the project.
What happens if it rains during the build?
Since there are no mixes or concrete in the walls, rain affects the work less. Even so, the slab and the finishes depend on the weather.
Do the walls arrive finished?
They arrive assembled and numbered. On site they are fixed and closed with cement board, glass wool and interior boards.